Lots of folks - abt 60 at least! - at meeting on NE Tillamook & 7th - grilling @PBOTinfo staff abt their plans for Lloyd to Woodlawn Greenway, specifically removal of traffic circle.
6
4
4
41
0
PBOT staff still here listening and taking questions. Project engineer just made new proposal:
- Let us move fwd w plan as-is (see our story for details)
- we will add more features like concrete barriers, speed bumps, etc..
- we will reopen diverter decisions from 2018 (!!)
2
1
12
PBOT 2018: we want to do all types of diversion & transform 7th Ave!
Some important Black residents in 2018: Hell no! That’s just more racism!
PBOT: OK. Sorry. We won’t do that.
PBOT now: Here’s the watered down plan.
Some residents now: No! We want diversion! 😯 🤦♀️
3
7
Negotiations continuing… PBOT really wants to start project because they have a contractor ready to start. Ppl are saying no, not without seeing a plan first. PBOT: “that takes too long, we can’t agree to that.” (Pic is PBOT planner Steve Szighety)
2
1
6
GIF
Not the outcome I expected! I hope I'll be able to see a copy of the plan too!